The company said it’s removing “some blades” from Vineyard Wind following an analysis of 8,300 ultrasound images per blade, ...
After review, some blades will be removed, and others will be reinforced. The post Vineyard Wind is given the OK to move ...
New Bedford in Massachusetts hosting Vineyard Wind’s installation is also the nation’s most valuable fishing harbour ...
The project is removing some blades and "strengthening other blades as needed to support the safety and operational readiness ...
According to GE Vernova, the turbine blade failure was was caused by a "material or manufacturing deviation" at a factory in ...
What Vineyard Wind needs to do before turning turbines south of Nantucket back on. The wind farm has been offline since a ...
Vineyard Wind early Wednesday morning revealed that it has been given approval to resume installation of turbine blades after ...
A spokesperson said power production "will resume only after additional progress is made and all requisite approvals are ...
In a Sept. 27 letter addressed to Vineyard Winds’ chief executive and its director of permitting, the Bureau of Safety and ...
An accident at the high-profile Massachusetts project over the summer saw one of its blades detach and plunge into the ocean.
It indicates to me that there appear to be more issues with more blades than just the one, and that’s as much as I know,” ...
The company's reported Q3 loss fell to $99M, or $0.35/share, from a loss of $185M, or $0.62/share in the year-earlier quarter ...